Amazon, Google, Meta and Microsoft have locked in tens of gigawatts of natural gas capacity in recent years to power their rapidly growing AI data centres. That strategy implicitly assumed stable or low gas prices. Research firm Noreva now warns that prices in some US regions could eventually triple, rising to more than ten dollars per million BTU, while most regions currently sit between two and 4.50 dollars.
According to Noreva, the expected price increase is driven by the combination of rapidly rising demand from the tech sector, slower-growing gas supply, and increasing exports of liquefied natural gas (LNG). How significant the risk turns out to be for hyperscalers depends on whether, and how quickly, those market conditions actually materialise.
Billions committed to gas
The scale of the investments makes the potential exposure tangible. Meta, through utility company Entergy, has had seven additional gas plants planned in Louisiana, bringing the total gas capacity for the Hyperion data campus to 7.46 gigawatts. Amazon is building a gas-fired power plant of 7.6 gigawatts in Texas. Microsoft signed a letter of intent for 1.4 gigawatts of so-called 'behind-the-meter' gas generation in West Virginia, and is in exclusive talks with Chevron and Engine No. 1 about a 2.5-gigawatt plant in West Texas. Google is exploring on-site gas generation for its Goodnight data campus in Texas in collaboration with Crusoe Energy, and last year purchased power from a 400-megawatt gas plant with carbon capture in Illinois.
Enverus Intelligence Research (EIR) estimates hyperscalers' cumulative capital expenditure for the period 2026 through 2030 at approximately five trillion dollars. More than eighty percent of projected data centre expansion through 2030 is taking place within the grid systems PJM, ERCOT, MISO and WECC.
What a price spike means in practice
How sharply gas prices can move was demonstrated in January 2026. A twenty percent national surge in demand drove the Henry Hub price, the US gas benchmark in Louisiana, from an average of 7.75 dollars per million BTU to 30 dollars, an increase of four hundred percent in a short period. That spike was temporary, but it illustrates how sensitive the market is to demand shocks.
Peter Gardett, CEO of Noreva, argues that prices at certain delivery hubs could structurally exceed ten dollars per million BTU. For comparison, the Henry Hub price was below three dollars at the time of the forecast. Energy costs currently account for roughly ten percent of hyperscalers' total costs. If gas prices sustainably double or triple, that share could rise to twenty to thirty percent by 2029, according to Noreva.
Structural factors behind the expected price increase
Rising demand from data centres is only one side of the story. On the supply side, US LNG export capacity is steadily expanding, placing additional pressure on the domestic gas balance. At the same time, growth in new gas production is lagging behind the increase in demand.
Analysts at 451 Research, part of S&P Global, and researchers at the Center on Global Energy Policy at Columbia University and the Center for Energy Studies at Rice University point to similar tensions in the gas market, although forecasts differ by institution in terms of pace and magnitude. The International Energy Agency and PwC, which in their Global Infrastructure Outlook 2025–2050 project cumulative global infrastructure investment of 151.1 trillion dollars over 25 years, also factor in structurally higher energy demand worldwide.
What this means for the Dutch and European AI scene
The dynamics of the US market also have implications for the broader European context. Dutch and European hyperscale operators and their suppliers closely monitor the energy strategies of large US tech companies, as these set the precedents for long-term contracts and energy mix choices. The debate around data centres' dependence on gas has been ongoing in Europe for some time, partly due to higher European energy prices since 2022 and pressure from EU policy to reduce the digital sector's carbon footprint. If American hyperscalers are forced by rising gas prices to reconsider their energy strategy, that could also accelerate demand for alternative energy sources, long-term renewable power purchase agreements (PPAs) and demand-response technology in Europe. For Dutch investors and policymakers focused on data centre infrastructure and the energy transition, developments in the US are therefore a relevant indicator.